Update from Councillor Schule on projects within Langdon
Langdon Fire Hall
Work is proceeding as expected and the project continues to trend on budget. Specific items of
interest include:
- Contract for Architectural Design was awarded in May 2019
- Purchase of the new property (24 – 3rd Avenue) was completed in June 2019
- Engineering is well underway and a building permit application is planned for September 2019
- Site preparation (clearing, rough grading, servicing) is planned for September/October
- Major construction is expected to begin in the Spring of 2020 and last 14 to 16 months
Langdon Fourth Street Walkway
- The sections of pathway completed in 2018 held up very well over the winter, and minimal touch-up work is required
- 2019 work began on June 6th but was subsequently delayed due to extremely wet subsurface conditions
- We expect the ground to be sufficiently dried out by mid-July; Work will begin immediately thereafter and last approximately two weeks
Langdon Centre Street Improvements
- Detailed engineering is substantially complete
- 2019 construction will focus on pedestrian access (sidewalks and pathways) and some overland drainage improvements
- 2019 construction tender/award will be complete in July 2019, with construction planned in August 2019 (Specific dates will clear once the contract has been awarded)
- 2020 construction will focus on roadway improvements (vehicle lanes) and the underground stormwater line (Pending budget approval)